PPL-Blackstone JV CCGT Plants
TBD, (PA, TBD) County
A data center project in TBD, (PA, TBD) County, and the end user has not been named publicly.
The project by the numbers
Proposed for TBD, (PA, TBD) County
- Tenant
- Not disclosed. No end user has been named publicly.
- Current stage
- Joint venture formed and capitalized as Invitium Energy, with land and turbine deposits secured and Pennsylvania sites unannounced.
- Decision body
- TBD
- Top issues
- Residents and officials have focused on how little has been disclosed about the end user, water use, continuous mechanical noise, and emissions from backup generation.
PPL-Blackstone JV for new combined-cycle gas plants (2031+). Specific PA siting TBD. Supports QTS PA expansion. PPL and Blackstone Infrastructure announced a joint venture on July 15, 2025 at the Pennsylvania Energy and Innovation Summit to build, own, and operate new gas-fired combined-cycle generation serving data centers under long-term energy supply agreements. PPL said data center interest in its Pennsylvania territory alone had reached more than 60 GW of potential projects with over 13 GW in advanced planning, which if built would leave an estimated 6 GW generation shortfall within five to six years and about $15 billion in investment need. PPL's second-quarter 2026 Form 10-Q identifies the venture as Invitium Energy, LLC, owned 51 percent by PPL and 49 percent by Blackstone Infrastructure, and states it has secured multiple land parcels and placed deposits on future turbine purchases. Specific Pennsylvania sites have not been announced.
Coverage of this project
- 2026-06-30 U.S. Securities and Exchange CommissionPPL Corporation Form 10-Q (Invitium Energy joint venture)JV named Invitium Energy, 51/49 PPL-Blackstone; land parcels and turbine deposits secured
- 2025-07-15 PPL CorporationPPL Corporation and Blackstone Infrastructure create joint venture to build natural gas generation in PennsylvaniaJV announced; 60 GW of data center interest in PPL territory, 6 GW projected shortfall
Know your rights
In Pennsylvania, a data center on industrial land usually needs a special exception or conditional use, decided by a local Zoning Hearing Board after a public, quasi-judicial hearing. Neighbors can request party status, cross-examine witnesses, and build an evidentiary record. Municipalities can also write data-center ordinances with enforceable standards.
Know your rights →Take action
Organized community opposition is the single most effective check on these projects in Pennsylvania. Show up to hearings, submit comment when it is taken, support legal and expert-witness costs, and ask your municipality for a moratorium and a real ordinance.
How communities push back →