PNK Group / Great Stream Commons

Gregg Township (Allenwood), Union County

A 300 megawatt campus of roughly 1,500,000 square feet proposed for Gregg Township (Allenwood), Union County, and the end user has not been named publicly.

ContestedLargeBrownfieldN Central
At a glance

The project by the numbers

StatusApplication Filed
Capacity300 MW
Footprint1,500,000 sq ft
First announced2025
Target onlineTBD

Filed and under review in Gregg Township (Allenwood), Union County

The number that mattersThe plans cover roughly 1,500,000 square feet of building.
Tenant
Not disclosed. No end user has been named publicly.
Current stage
Curative amendment and conditional use applications under township review after a heated late-July public hearing.
Decision body
Gregg Township (Allenwood)
Top issues
Residents and officials have focused on electricity demand and grid capacity, the sheer footprint of the buildings, what remains in the ground from the site's industrial past, how little has been disclosed about the end user, water use, continuous mechanical noise, and emissions from backup generation.
Key opponents
Gregg Twp residents (Kay McCarty, Lisa Hollenbach, Rebecca DeWire among speakers)
Key supporters
Industrial-park siting; existing building reuse

PNK proposal became public 2026; supervisors hired attorney Rick Shoch May 4 2026 to draft an ordinance; hearing moved to June. A Gregg Township public hearing in late July 2026 ran nearly four hours before more than 150 residents, many wearing red in opposition. PNK is seeking a curative amendment and conditional use approval, with a plan to retrofit the existing 478,000 sq ft warehouse into a data center in 2027 and add three buildings by 2029, and says it has moved the substation and chillers to reduce noise and will use closed-loop cooling.

Community response

Who is organizing against it

Gregg Township residents (Great Stream Commons)

Single-project ยท Founded 2026

Leaders: (Kay McCarty, Lisa Hollenbach, Rebecca DeWire among speakers)

Tactics: 110+ resident turnout at supervisor meetings, pushing for a protective data-center ordinance

Residents pressing Gregg Twp (Union Co) on PNK Group's Great Stream Commons proposal (P025).

News

Coverage of this project

Know your rights

In Pennsylvania, a data center on industrial land usually needs a special exception or conditional use, decided by a local Zoning Hearing Board after a public, quasi-judicial hearing. Neighbors can request party status, cross-examine witnesses, and build an evidentiary record. Municipalities can also write data-center ordinances with enforceable standards.

Know your rights →

Take action

Organized community opposition is the single most effective check on these projects in Pennsylvania. Show up to hearings, submit comment when it is taken, support legal and expert-witness costs, and ask your municipality for a moratorium and a real ordinance.

How communities push back →