Water
HighOpponents say the campus could consume nearly as much potable water annually as all Frackville residences combined; water shared by Frackville, Butler Twp, and Ashland; conservation buffer at risk.
Skook NewsNew Castle Township, Schuylkill County
A data center project in New Castle Township, Schuylkill County, and the end user has not been named publicly.
Plans first reported 2025 (Coal Region Canary); KRNL bought a parcel for $600K; supervisors declared zoning invalid 3-0 Nov 11 2025; packed amendments meeting May 5 2026.
Opponents say the campus could consume nearly as much potable water annually as all Frackville residences combined; water shared by Frackville, Butler Twp, and Ashland; conservation buffer at risk.
Skook NewsSeveral eight-story structures ~850 ft long on a forested conservation hillside that buffers Frackville from I-81.
Skook NewsSave Frackville opposition; New Castle Twp 3-0 declared zoning invalid May 2026.
Tactics: Township-meeting turnout, zoning-validity advocacy
Opposed KRNL Data Centers (P042); New Castle Twp declared zoning invalid 3-0 (May 2026).
Leaders: Ryan Twardzik (organizer; son of State Rep. Tim Twardzik R-123); Victoria Domalakes
Tactics: Packed New Castle Twp meetings (overflow crowds), opposition letters from Frackville Borough + West Mahanoy Twp, pressing for 1,000-ft setbacks and keeping the parcel Conservation-zoned
Opposes KRNL's New Castle Twp campus (P042). Notable because the impacts fall on neighboring Frackville/Walnick Manor, which can't vote in New Castle. Allied with State Rep. Tim Twardzik.
Supervisors declared a portion of the zoning code invalid 3-0, triggering an MPC curative period to rewrite data-center rules before any KRNL application could proceed.
New Castle Twp (re: KRNL interest) · In ~6-month cure; amendments advanced May 2026In Pennsylvania, a data center on industrial land usually needs a special exception or conditional use, decided by a local Zoning Hearing Board after a public, quasi-judicial hearing. Neighbors can request party status, cross-examine witnesses, and build an evidentiary record. Municipalities can also write data-center ordinances with enforceable standards.
Know your rights →Organized community opposition is the single most effective check on these projects in Pennsylvania. Show up to hearings, submit comment when it is taken, support legal and expert-witness costs, and ask your municipality for a moratorium and a real ordinance.
How communities push back →