Environmental justice and site legacy
HighClifton Twp substantive validity challenge; Delaware Riverkeeper concerns.
Clifton + Covington Townships, Lackawanna County
A 1,500 megawatt campus of roughly 9,400,000 square feet proposed for Clifton + Covington Townships, Lackawanna County, and the end user has not been named publicly.
Presented to Covington May 13 2025 (rep Tony Maras); preliminary land-development + validity challenge filed; ordinances under review with developer contesting height limits (2025–2026).
Clifton Twp substantive validity challenge; Delaware Riverkeeper concerns.
PPL feasibility report cites up to 1,500 MW transmission load, over half the peak load of Duquesne Light's entire territory.
Data Center DynamicsTactics: Detailed document-based analysis of the Gouldsboro filings, township-meeting turnout, opposition to substantive-validity challenge and SALDO applications
Tracks the 1,000-acre, up-to-35-building Gouldsboro campus straddling Clifton + Covington (Lackawanna Co). Surfaced the PPL feasibility report citing up to 1,500 MW.
Substantive validity challenge to Clifton Twp zoning ordinance.
Project opponents · PendingChallenge claims Clifton's zoning ordinance is unconstitutional for failing to provide for data-center uses; seeks site-specific relief (the Gouldsboro campus).
1778 Rich Pike LLC vs Clifton Twp · PendingIn Pennsylvania, a data center on industrial land usually needs a special exception or conditional use, decided by a local Zoning Hearing Board after a public, quasi-judicial hearing. Neighbors can request party status, cross-examine witnesses, and build an evidentiary record. Municipalities can also write data-center ordinances with enforceable standards.
Know your rights →Organized community opposition is the single most effective check on these projects in Pennsylvania. Show up to hearings, submit comment when it is taken, support legal and expert-witness costs, and ask your municipality for a moratorium and a real ordinance.