PATER site tracker
Part A candidate

Lock Haven

Clinton County · No street address in the report

A fuel oil peaker plant that retired in 2022 with 18.5 MW of capacity, on a 33.97-acre parcel in Clinton County. The PATER study evaluates it for new generation.

PPL zoneEvaluated for new generationDistillate Fuel OilRetired 2022
At a glance

The site by the numbers

Retired capacity18.5 MW
Retired in2022
Parcel33.97 acres
Adjacent land0 acres
Within 30 miles239,464 people
From 900 Conshohocken Rd133.6 miles
Section 4.12

What the report says about this site

“Located at no specific address but at coordinates 41°07'08.0"N 77°28'15.7"W, this former fuel oil peaker plant located across Balk Eagle Creek from Flemington PA retired in 2022 and has a retired capacity of 18.5 MW (see Figure 28 and Table 17). Pennsylvania Power and Light Co. has plans to rebuild the lock haven substation and Sunbury–Lock Haven 69-kV line here. The 34-acre site is located between Flemington and Mill Hall. The site is decommissioned, but its remediation status is unknown. It is zoned for commercial use and rated as nearly level. The site is not classified as a presumptive brownfield, and there is no known soil or groundwater contamination. FEMA designates the site as having a relatively low natural hazard risk but sitting in a floodway. The parcel and nearby parcels are not located within or adjacent to a documented coal mining area and are, therefore, considered to have minimal mine subsidence potential. The site has easy major road and rail access, and river access is ~2.5 miles away. The site has immediate access to transmission lines and a substation, but a natural gas pipeline is ~11 miles away. The nearest broadband installation is ~20 miles away. The nearest generator is ~33 miles away. The site sits ~1 mile from the Marcellus shale formation. The nearest wastewater treatment plant and brownfield are ~2 miles away. There are ~239,464 people within 30 miles of the site.”

PATER Part A report, section 4.12, page 46
Table 17

Site attributes

Report name
Lock Haven (PENNPOW)
Address
No street address in the report
Coordinates
41°07'08.0"N 77°28'15.7"W
Fuel
Distillate Fuel Oil
Zoning
Commercial
Ruggedness
1 = Nearly level
Brownfield designation
Not Presumptive
On-site contamination
None known
Groundwater contamination
None known
FEMA natural hazards risk
Relatively low
FEMA flood hazard
Floodway
Population within 30 miles
About 239,464 (report estimate)
PJM transmission zone
PPL
Evaluated for
New generation
Table 17

Distance to infrastructure

Approximate distance in miles, as published in Table 17 (page 46). The report says distances are measured from a point on the site and “all distance measurements must be considered general.”
Distance toMiles
Major road0.25
Rail network0.23
Major river2.42
Transmission line0.00
Substation0.00
Natural gas pipeline11.34
Broadband20.32
Marcellus Shale formation0.88
Wastewater treatment facility2.22
Brownfield site2.12
Table 28

The report’s acreage-based capacity estimates

Installed capacity potential in megawatts, from Table 28 (pages 78 and 79). The report calls these estimates “approximate as they are based on parcel acreage (which may differ from developable land acreage) and single land use intensity values per technology.” The gas figure is the acreage divided by 0.2 acres per megawatt (Table 27). Extended acreage adds adjacent parcels with the same owner.
TechnologyParcel (34 acres)Extended (34 acres)
Natural gas170170
Conventional nuclear5757
Battery storage485485
Solar55

The report places sites in the PPL transmission zone in its generation category, because projected load growth there exceeds expected generation additions (pages 76 and 77).

Status

Where this site stands

Current status
Part A candidate. Part B will narrow the 21 sites to 5 to 7 priorities.
Next step
Part B will rank the sites and validate the top 5 to 7 through site visits (page 103).
Public comment
Written comments on Part A are accepted under PUC Docket No. M-2026-3059601 through October 14, 2026.
Review meetings
The report says PATER Study Review Meetings are planned for October and February (page 103).

Our view on the study

Pennsylvania is studying two Schuylkill power sites. We think residents deserve corrected data, real environmental analysis and a straight answer on costs before the list gets shorter.

Read our view →

Take action

File a comment by October 14, watch the October 7 review meeting, and come to the Zoning Hearing Board on Thursday, October 15 at 7:00 p.m.

Ways to help →