AES Beaver Valley
Beaver County · 400 Frankfort Rd, Monaca, PA 15061
A coal plant that retired in 2015 with 149 MW of capacity, on a 196-acre parcel in Beaver County. The PATER study evaluates it for new generation or large load.
The site by the numbers
What the report says about this site
“Located at 400 Frankfort Rd, Monaca, PA 15061 (coordinates 40°40'03.0"N 80°21'12.5"W), and also known as the Beaver Valley Generation Plant, this 196-acre former coal plant on the Ohio River and Raccoon Creek retired in 2015 and has a retired capacity of 149 MW (see Figure 17 and Table 6). The facility occupied leased land within a 196-acre parcel owned by Nova Chemicals. The lease was terminated in 2015 following an early buyout of the power purchase agreement by West Penn Power, the plant’s primary customer (Utility Dive, 2015). Ownership of the parcel transferred to Styropek (i.e., BVPV Styrenics, LLC) in 2020 (The Allegheny Front, 2023). Styropek ceased operations in 2026, and county property records show that the site was acquired by Beaver County Redevelopment Co. LLC, a redevelopment entity, in April 2026. It is zoned for industrial use and has 54.9 adjacent acreage possibly open for further redevelopment space, though the terrain is rated as highly rugged. The site is treated as a presumptive brownfield with soil and groundwater contamination to be determined (TBD). FEMA designates the site as having a very low natural hazard risk with minimal flood hazard. The parcel and nearby parcels are designated as having possible mine subsidence potential, as they are located within or adjacent to a known coal mining area; however, no publicly accessible PA DEP records were identified to confirm that mining activities occurred on the site. The site has immediate access to the road network, the rail network, and a river. Transmission lines, a substation, and a natural gas pipeline are all available within 1 mile; Broadband, the closest generation plant, the Marcellus shale formation, and a wastewater treatment facility are all available within 5 miles. The nearest brownfield site is ~6 miles away. There are ~1,421,408 people within 30 miles of the site.”
PATER Part A report, section 4.1, page 35
Site attributes
- Report name
- AES Beaver Valley Partners Beaver Valley
- Address
- 400 Frankfort Rd, Monaca, PA 15061
- Coordinates
- 40°40'03.0"N 80°21'12.5"W
- Fuel
- Coal
- Zoning
- Industrial
- Ruggedness
- 5 = Highly rugged
- Brownfield designation
- Presumptive
- On-site contamination
- TBD
- Groundwater contamination
- TBD
- FEMA natural hazards risk
- Very low
- FEMA flood hazard
- Minimal
- Population within 30 miles
- About 1,421,408 (report estimate)
- PJM transmission zone
- DUQ
- Evaluated for
- New generation or large load
Distance to infrastructure
| Distance to | Miles |
|---|---|
| Major road | 0.08 |
| Rail network | 0.12 |
| Major river | 1.16 |
| Transmission line | 0.70 |
| Substation | 0.13 |
| Natural gas pipeline | 0.72 |
| Broadband | 1.10 |
| Marcellus Shale formation | 0.00 |
| Wastewater treatment facility | 2.04 |
| Brownfield site | 5.89 |
The report’s acreage-based capacity estimates
| Technology | Parcel (196 acres) | Extended (251 acres) |
|---|---|---|
| Natural gas | 980 | 1,255 |
| Conventional nuclear | 327 | 418 |
| Battery storage | 2,800 | 3,585 |
| Solar | 28 | 36 |
The report evaluated sites in the DUQ transmission zone for both new generation and new large loads, because the difference between expected load and generation there was marginal (page 79).
Where this site stands
- Current status
- Part A candidate. Part B will narrow the 21 sites to 5 to 7 priorities.
- Next step
- Part B will rank the sites and validate the top 5 to 7 through site visits (page 103).
- Public comment
- Written comments on Part A are accepted under PUC Docket No. M-2026-3059601 through October 14, 2026.
- Review meetings
- The report says PATER Study Review Meetings are planned for October and February (page 103).
All 21 candidate sites
- Barbadoes Island2.7 mi
- Venice Island (JSC)5.7 mi
- Cromby12.1 mi
- Martins Creek Harwood69.5 mi
- West Shore86.3 mi
- Jenkins86.6 mi
- Stanton92.5 mi
- Lock Haven133.6 mi
- Milesburg142.6 mi
- Williamsburg154.6 mi
- Cambria Cogeneration180.4 mi
- Armstrong Power Station225.6 mi
- Piney Creek229.0 mi
- Elrama Power Plant243.1 mi
- Hatfield's Ferry244.6 mi
- Mitchell Power Station245.8 mi
- F R Phillips260.8 mi
- Wayne264.5 mi
- AES Beaver Valley268.1 mi
- North East Cogeneration277.1 mi
- Erie Mill284.4 mi
Our view on the study
Pennsylvania is studying two Schuylkill power sites. We think residents deserve corrected data, real environmental analysis and a straight answer on costs before the list gets shorter.
Read our view →Take action
File a comment by October 14, watch the October 7 review meeting, and come to the Zoning Hearing Board on Thursday, October 15 at 7:00 p.m.
Ways to help →